Docket 29849

Georgia Power Company`s Vogtle Units 3 and 4 Construction Monitoring

contested This docket on the Commission's site

Industry (Commission's label)Electric
Opened2011-12-18
StatusOpen
Filings in the record167
First and last filed2022-05-05 to 2024-10-10
Staff unitElectric
CommitteeEnergy
Files159 of 167 filings have a file to download; 8 with no file posted
Parties that filed a disagreementConcerned Ratepayers of Georgia; Georgia Power Company; Staff

Filings, newest first

FiledFilerFiling
2024-10-10Georgia Power CompanyDKT 29849 STF-260 Data Request Responses PD
Download fileElectric
2024-09-10StaffData Request from Commission Staff (STF-260)
Download fileElectric
2024-09-06Georgia Power CompanySTF-71-33 PD Data Request Response
Download fileElectric
2024-08-30Georgia Power CompanySemi-Annual Vogtle Construction Monitoring Report VCM-31
Download fileElectric
2024-08-28StaffData Request from Commission Staff (STF-259)
Download fileElectric
2024-08-22Georgia Power CompanySTF-258 Data Request Responses
Download fileElectric
2024-08-19Georgia Power CompanySTF-257 Data Request Responses PD
Download fileElectric
2024-07-23StaffData Request from Commission Staff (STF-258)
Download fileElectric
2024-07-19StaffData Request from Commission Staff (STF-257)
Download fileElectric
2024-06-17Georgia Power CompanyDKT 29849 STF-256 Data Request Responses PD
Download fileElectric
2024-05-20Georgia Power CompanyApr 2024 Vogtle Monthly Status Report PD
Download fileElectric
2024-05-16StaffData Request from Commission Staff (STF-256)
Download fileElectric
2024-05-16StaffData Request from Commission Staff (STF-256)
Download fileElectric
2024-05-14Concerned Ratepayers of GeorgiaCRG RESPONSE TO CORRECTING ORDER DENYING PETITION FOR REHEARING AND FOR RECONSIDERATION
Download fileElectricrehearing or reconsideration
2024-05-08GPSCORDER CORRECTING ORDER DENYING PETITION FOR REHEARING AND FOR RECONSIDERATION
2 files to downloadElectricrehearing or reconsideration
2024-05-06Southern Alliance for Clean EnergyNotice of Withdrawal and Substitution
Download fileElectric
2024-04-29Georgia Power CompanyDKT 29849 - Vogtle Unit 4 Commercial Operation Notification
Electric
2024-04-26Georgia Power CompanyVogtle Unit 4 COD Tariffs & MFR Filing
Download fileElectric
2024-04-22Georgia Power CompanyDKT 29849 March 2024 Monthly Status Report PD
Download fileElectric
2024-04-16Concerned Ratepayers of GeorgiaCRG Response to Commission denial of motion for Reconsideration
Download fileElectricrehearing or reconsiderationresponse to another party's motion
2024-04-11GPSCORDER DENYING PETITION FOR REHEARING AND FOR RECONSIDERATION
2 files to downloadElectricrehearing or reconsideration
2024-04-11Georgia Power CompanyDKT 29849 STF-255 Data Request Responses
Download fileElectric
2024-04-05Georgia Power CompanyDKT 29849 STF-254 Data Request Responses
Download fileElectric
2024-03-20Georgia Power CompanyDKT 29849 February 2024 Monthly Status Report
Download fileElectric
2024-03-11StaffData Request from Commission Staff (STF-255)
Download fileElectric
2024-03-08Georgia Power CompanyDKT 29849 STF-71-33 Supplemental Data Request Response - VCM 30 PD
Download fileElectric
2024-03-06StaffData Request from Commission Staff (STF-254)
Download fileElectric
2024-02-27Concerned Ratepayers of GeorgiaCRG RESPONSE TO GA POWER & PSC STAFF OBJECTION TO PETITION FOR REHEARING & RECONSIDERATION
Download fileElectricobjectionrehearing or reconsideration
2024-02-22Georgia Power CompanyGeorgia Power Company's Response to Concerned Ratepayers of Georgia's Petition for Rehearing and Reconsideration
Download fileElectricrehearing or reconsideration
2024-02-21StaffResponse to The Petition for Rehearing and Reconsideration
2 files to downloadElectricrehearing or reconsideration
2024-02-20Georgia Power CompanyDKT 29849 Vogtle Monthly Status Report for January 2024
Download fileElectric
2024-02-15Georgia Power CompanyDKT 29849 VCM 30 Semi-Annual Report
Download fileElectric
2024-02-12Concerned Ratepayers of GeorgiaCRG's PETITION FOR REHEARING & RECONSIDERATION Of PRUDENCY ORDER
Download fileElectricrehearing or reconsideration
2024-01-31GPSCORDER ADOPTING STIPULATION
2 files to downloadElectric
2024-01-22Georgia Power CompanyDKT 29849 Monthly Status Report for December 2023 PD
Download fileElectric
2024-01-17Georgia Power CompanyDKT 29849 STF-253 Data Request Responses
Download fileElectric
2024-01-03Concerned Ratepayers of GeorgiaCRG's VIDEO OF STAFF ATTORNEY THOMAS’ CONDESCENDING COMMENTS ABOUT PATTY DURAND & COMMISSIONER JOHNSON EVICTING PRENOVITZ FROM HEARING ROOM -- Vogtle Prudence Review 12-14-2023
Download fileElectric
2023-12-20Georgia Power CompanyDKT 29849 Vogtle Monthly Status Report for November 2023
Download fileElectric
2023-12-19StaffData Request from Commission Staff (STF-253)
Download fileElectric
2023-12-18Concerned Ratepayers of GeorgiaCRG RESPONSE TO COMMISSIONER JOHNSON EVICTING PRENOVITZ FROM HEARING ROOM - Vogtle Prudence Review 12-14-2023
Download fileElectric
2023-12-12Resource Supply ManagementBrief of Resource Supply Management
Download fileElectric
2023-12-11StaffProposed Order Adopting Stipulated Agreement
3 files to downloadElectric
2023-12-11Georgia Power CompanyGeorgia Power Company's Prudency Post-Hearing Brief and Proposed Order
Download fileElectric
2023-12-11Concerned Ratepayers of GeorgiaADDENDUM TO POST HEARING BRIEF OF CONCERNED RATEPAYERS OF GEORGIA -- Vogtle Prudency & Reasonableness Review Doc # 29849
Download fileElectric
2023-12-11Southern Alliance for Clean EnergyPOST-HEARING BRIEF OF SOUTHERN ALLIANCE FOR CLEAN ENERGY
Download fileElectric
2023-12-11Georgia Interfaith Power & Light and Partnership for Southern EquityGeorgia Interfaith Power & Light, Partnership for Southern Equity
Download fileElectric
2023-12-11Concerned Ratepayers of GeorgiaCRG- Prenovitz & Durand Prudency Brief re: GA Power’s application to adjust rates to include Reasonable & Prudent Vogtle units 3 & 4 cost
Download fileElectric
2023-11-22StaffStaff's Response to Nuclear Watch South and Georgia Wand's Petition to Hold In Abeyance
2 files to downloadElectric
2023-11-20Georgia Power CompanyDKT 29849 - Vogtle Monthly Status Report for Oct 2023 PD
Download fileElectric
2023-11-20Georgia Power CompanyDKT 29849 STF-252 Data Request Responses
Download fileElectric
2023-11-16Georgia Power CompanyRebuttal Testimony n Support of Georgia Power's Application to Adjust Rates
Download fileElectric
2023-11-01Georgia Power CompanyDKT 29849 - Georgia Power Company’s Application to Adjust Rates to Include Reasonable and Prudent Plant Vogtle 3 and 4 Costs
Download fileElectric
2023-10-27StaffDirect Testimonies, Reports, Attachments, and Exhibits of the Panel of Reza Nikain, Mark W. Cohen, and Rob Strahle of J.S Held and Associates
10 files to downloadElectric
2023-10-27StaffDirect Testimonies, Reports, Attachments, and Exhibits of the Panel of Steve Roetger and William R. Jacobs Jr, Donald N. Grace, and Lane Kollen
7 files to downloadElectric
2023-10-27Nuclear Watch South, Georgia WANDPETITION TO HOLD IN ABEYANCE
2 files to downloadElectric
2023-10-26Concerned Ratepayers of GeorgiaPatty Durand -- Expert witness prudency testimony
Download fileElectric
2023-10-20Georgia Power CompanyDKT 29849 - Vogtle Monthly Status Report for September 2023
Download fileElectric
2023-10-19StaffData Request from Commission Staff (STF-252)
Download fileElectric
2023-10-10Georgia Power CompanyDKT 29849 Vogtle 3 & 4 Prudence Legal Notice
Download fileElectric
2023-10-06Resource Supply ManagementResource Supply Management ‘s Application for Leave to Intervene and Comments on Prudence
2 files to downloadElectric
2023-09-28Georgia WatchIntervention Petition Vogtle Prudency
Download fileElectric
2023-09-28Georgia WatchIntervention Petition VCM 29
Download fileElectric
2023-09-20Georgia Interfaith Power & Light and Partnership for Southern EquityJoint Application for Leave to Intervene - Prudency
Download fileElectric
2023-09-20Georgia Interfaith Power & Light and Partnership for Southern EquityJoint Application for Leave to Intervene in VCM 29
Download fileElectric
2023-09-20Georgia Power CompanyDKT 29849 Vogtle Monthly Status Report for August 2023 PD
Download fileElectric
2023-09-11Georgia Power CompanyDKT 29849 STF-251 Data Request Responses
Download fileElectric
2023-09-08Southern Alliance for Clean EnergySACE Petition to Intervene in VCM29
Download fileElectric
2023-09-08Southern Alliance for Clean EnergySACE Petition to Intervene in Georgia Power Company’s Application to Adjust Rates to Include Reasonable and Prudent Plant Vogtle Units 3 and 4 Costs
Download fileElectric
2023-09-08Georgia Power CompanyDKT 29849 Prudence Testimony
4 files to downloadElectric
2023-09-08Concerned Ratepayers of GeorgiaCRG Motion to Intervene in GA Power's VCM 29
Download fileElectric
2023-09-06GPSCPROCEDURAL AND SCHEDULING ORDER
2 files to downloadElectric
2023-09-05Georgia Association of ManufacturersApplication for Leave to Intervene - Vogtle Prudency Hearings
Download fileElectric
2023-09-05Georgia Association of ManufacturersApplication for Leave to Intervene - VCM-29
Download fileElectric
2023-09-05Concerned Ratepayers of GeorgiaCRG application to Intervene i,re: GA Power's application to adjust rates to include reasonable and Prudent Vogtle units 3 & 4 costs
Download fileElectric
2023-09-01StaffProposed PROCEDURAL AND SCHEDULING ORDER Georgia Power Company’s Application to Adjust Rates to Include Reasonable and Prudent Plant Vogtle Units 3 and 4 Costs
Download fileElectric
2023-08-30Georgia Power CompanyDKT 29849 VCM-29 Semi-Annual Report
Download fileElectric
2023-08-30Georgia Power CompanyVogtle 3 and 4 Prudence Application
4 files to downloadElectric
2023-08-30StaffProposed Stipulated Agreement in Georgia Power Company's Application to Adjust Rates to Include Reasonable and Prudent plant Vogtle Unit 3 and 4 Costs; Docket 29849
3 files to downloadElectric
2023-08-21Georgia Power CompanyDKT 29849 July 2023 Monthly Status Report PD
Download fileElectric
2023-08-10StaffData Request from Commission Staff (STF-251)
Download fileElectric
2023-08-07Georgia Power CompanyDKT 29849 STF-250 Data Request Responses
Download fileElectric
2023-08-03Georgia Power CompanyGeorgia Power Company's Notice of No Rebuttal Testimony for VCM 28
Download fileElectric
2023-08-03Hearing TranscriptHearing held on Thursday, July 7, 2023
Electric
2023-08-02Concerned Ratepayers of GeorgiaCRG Brief- VCM28
Download fileElectric
2023-07-20Georgia Power CompanyDKT 29849 Vogtle Monthly Status Report for June 2023
Download fileElectric
2023-07-05StaffData Request from Commission Staff (STF-250)
Download fileElectric
2023-06-22StaffDIRECT TESTIMONY AND EXHIBITS OF STEVEN D. ROETGER WILLIAM R. JACOBS, JR., PhD.
3 files to downloadElectric
2023-06-22StaffDIRECT TESTIMONY AND EXHIBITS OF TOM NEWSOME, PE, CFA PHILIP HAYET LANE KOLLEN, CPA, CMA, CGMA
3 files to downloadElectric
2023-06-22StaffDIRECT TESTIMONY AND EXHIBIT OF SHEMETHA Q. JONES
3 files to downloadElectric
2023-06-20Georgia Power CompanyDKT 29849 Vogtle Monthly Status Report for May 2023
Download fileElectric
2023-06-20Georgia Power CompanyDKT 29849 STF-249 Data Request Responses
Download fileElectric
2023-06-20Concerned Ratepayers of GeorgiaPrenovitz-- Direct testimony & Exhibits for VCM 28
Download fileElectric
2023-06-07TranscriptTranscript for Hearing held on Thursday, June 1, 2023
Electric
2023-06-05Georgia Power CompanyDKT 29849 STF-248 Data Request Responses
Download fileElectric
2023-06-05Georgia Power CompanyDKT 29849 STF-247 Data Request Responses
Download fileElectric
2023-05-26Georgia Power CompanyGeorgia Power Company's Demonstrative Slides for VCM 28 Hearing
Download fileElectric
2023-05-22Georgia Power CompanyDKT 29849 Vogtle Monthly Status Report for April 2023 PD
Download fileElectric
2023-05-18StaffData Request from Commission Staff (STF-249)
Download fileElectric
2023-05-15Georgia Power CompanyDKT 29849 STF-245 Data Request Responses
Download fileElectric
2023-05-05Georgia Power CompanyVCM 28 Direct Testimony of John B. Williams and Jeremiah Haswell on Behalf of Georgia Power Company
Download fileElectric
2023-05-05StaffData Request from Commission Staff (STF-248)
Download fileElectric
2023-05-04StaffData Request from Commission Staff (STF-247)
Download fileElectric
2023-04-20Georgia Power CompanyDKT 29849 Mar 2023 Monthly Status Report
Download fileElectric
2023-04-14Nuclear Watch SouthPetition to Intervene
2 files to downloadElectric
2023-04-13StaffData Request from Commission Staff (STF-245)
Download fileElectric
2023-03-27Georgia WatchIntervention Petition
Download fileElectric
2023-03-27Southern Environmental Law CenterNotice of Withdrawal of Counsel
Download fileElectric
2023-03-27Georgia Interfaith Power & Light and Partnership for Southern EquityJoint Application of Georgia Interfaith Power & Light and Partnership for Southern Equity for Leave to Intervene
Download fileElectric
2023-03-24Georgia Power CompanyGeorgia Power Company's Notice of First Publication of the Legal Notice for VCM 28
Download fileElectric
2023-03-20Georgia Power CompanyDKT 29849 STF-244 Data Request Responses
Download fileElectric
2023-03-20Georgia Power CompanyDKT 29849 STF-243 Data Request Responses
Download fileElectric
2023-03-20Georgia Power CompanyDKT 29849 Vogtle Monthly Status Report for February 2023
Download fileElectric
2023-03-15StaffDocket No. 29849 / Georgia Power Company's 27th Vogtle Construction Monitoring (VMC 27): Georgia Watch Hearing Request
2 files to downloadElectric
2023-03-15GPSCPROCEDURAL AND SCHEDULING ORDER for VCM 28
2 files to downloadElectric
2023-03-15Georgia Association of ManufacturersApplication for Leave to Intervene
Download fileElectric
2023-03-14Southern Alliance for Clean EnergyApplication of the Southern Alliance for Clean Energy for Leave to Intervene in VCM28
Download fileElectric
2023-03-10Concerned Ratepayers of GeorgiaCRG -- VCM 28 Motion to Intervene
Download fileElectric
2023-03-02Georgia Power CompanyDKT 29849 STF-242 PD
Download fileElectric
2023-03-02Georgia Power CompanyDKT 29849 STF-241 PD
Download fileElectric
2023-03-02Georgia Power CompanyDKT 29849 STF-241 PD
Download fileElectric
2023-03-02Georgia Power CompanyDKT 29849 STF-71-33 PD
Download fileElectric
2023-02-23StaffData Request from Commission Staff (STF-244)
Download fileElectric
2023-02-21StaffData Request from Commission Staff (STF-243)
Download fileElectric
2023-02-20Georgia Power CompanyDKT 29849 Vogtle Monthly Status Report for January 2023
Download fileElectric
2023-02-20Georgia Power CompanyDKT 29849 STF-240 Data Request Responses
Download fileElectric
2023-02-16Georgia Power CompanyDKT 29849 TN-1-2 VCM28 PD
Download fileElectric
2023-02-16Georgia Power CompanyDKT 29849 VCM-28 Semi-Annual Report
Download fileElectric
2023-02-07Georgia Power CompanyGeorgia Power Company's Notice of No Rebuttal Testimony
Download fileElectric
2023-02-01StaffData Request from Commission Staff (STF-241)
Download fileElectric
2023-01-30Hearing TranscriptHearing Transcript dated Tuesday, January 17, 2023
Electric
2023-01-26Concerned Ratepayers of GeorgiaCRG Brief- VCM 27
Download fileElectric
2023-01-20Georgia Power CompanyDKT 29849 Vogtle Monthly Status Report for December 2022
Download fileElectric
2023-01-19StaffData Request from Commission Staff (STF-240)
Download fileElectric
2023-01-03StaffDirect Testimonies and Exhibits of Shemetha Jones, the Panel of Tom Newsome, Philip Hayet and Lane Kollen, with both Public Disclosure and Trade Secret Versions of the Panel of Steven D. Roetger and William R. Jacobs Jr.
9 files to downloadElectric
2022-12-30Concerned Ratepayers of GeorgiaPrenovitz/CRG Testimony & Exhibits VCM 27
2 files to downloadElectric
2022-12-20Georgia Power CompanyDKT 29849 Vogtle Monthly Status Report for November 2022 PD
Download fileElectric
2022-12-15Hearing TranscriptTranscript to Hearing held Tuesday, December 6, 2022
Electric
2022-12-08Georgia Power CompanyDKT 29849 STF-239 Data Request Responses
Download fileElectric
2022-12-05Georgia Power CompanyDKT 29849 STF-238 PD Data Request Responses
Download fileElectric
2022-12-02Georgia Power CompanyGeorgia Power Company's Demonstrative Slides for Use at December 6, 2022 Hearing
Download fileElectric
2022-12-01Georgia Power CompanyGeorgia Power Company Request to Combine Panels at Hearing
Download fileElectric
2022-11-21Georgia Power CompanyDKT 29849 Vogtle Monthly Status Report for October2022
Download fileElectric
2022-11-08StaffData Request from Commission Staff (STF-239)
Download fileElectric
2022-11-08Georgia Association of ManufacturersApplication for Leave to Intervene
Download fileElectric
2022-11-04StaffData Request from Commission Staff (STF-238)
Download fileElectric
2022-11-03Georgia Power CompanyDKT 29849 STF-237 Data Request Responses
Download fileElectric
2022-10-27Georgia Power CompanyGeorgia Power Company's Direct Testimony of the Panel of David L. McKinney and Jeremiah C. Haswell and the Panel of Stephen E. Kuczynski and John B. Williams
Download fileElectric
2022-10-27StaffStaff Response to Hearing Request VCM 26
2 files to downloadElectric
2022-10-26Georgia Power CompanyDKT 29849 STF-236 Data Request Response
Download fileElectric
2022-10-20Georgia Power CompanyDKT 29849 Vogtle Monthly Status Report (MSR) for September 2022 PD
Download fileElectric
2022-10-18Georgia WatchIntervention petition
Download fileElectric
2022-10-17Southern Environmental Law CenterJoint Application of Georgia Interfaith Power & Light and Partnership for Southern Equity for Leave to Intervene
Download fileElectric
2022-10-17Georgia Power CompanyDKT 29849 VCM 27 Notice of First Publication of Legal Notice
Download fileElectric
2022-10-07Georgia Power CompanyDKT 29849 STF-235 Data Request Responses
Download fileElectric
2022-10-07Georgia Power CompanyVCM 27 Errata Filing
Download fileElectric
2022-10-04StaffData Request from Commission Staff (STF-237)
Download fileElectric
2022-10-04GPSCPROCEDURAL AND SCHEDULING ORDER
2 files to downloadElectric
2022-09-30Georgia Power CompanyDKT 29849 Aug 2022 Monthly Status Report Supplemental PD
Download fileElectric
2022-09-30Georgia Power CompanyDKT 29849 STF-234 Data Request Responses
Download fileElectric
2022-09-30Concerned Ratepayers of GeorgiaCRG Motion to Intervene VCM 27
Download fileElectric
2022-09-28StaffData Request from Commission Staff (STF-236)
Download fileElectric
2022-09-23Georgia Power CompanySTF-71-33 Update Sept. 23, 2022
Electric
2022-09-21Georgia Power CompanyVogtle Monthly Status Report Supplemental Data Request Response STF-44-1
Download fileElectric
2022-09-21Southern Alliance for Clean EnergyApplication of the Southern Alliance for Clean Energy for Leave to Intervene
Download fileElectric
2022-09-20Georgia Power CompanyAugust 2022 Vogtle Monthly Status Report
Download fileElectric
2022-07-15GPSCTranscript from Hearing held on July 12, 2022
Electric
2022-05-05GPSCTranscript of Hearing held on May 3, 2022
Electric